Chapel Roof & Chapel Restoration Project
Quotation for the Proposed Restoration
Selected Contractor:
Mr. A. L. Rathnasiri
PHASE 1: Total Cost for Restoration of Roof: LKR 2,254,100.
Selected Contractor:
Jayawardhana Engineering
PHASE 2: Total Cost for Interior & Exterior Walls: LKR 3,261,850/-
The Total cost for Phase 1 & 2:
LKR 5,515,950